Top takeaways
If you only read one section, read this one.
- Vet everyone, especially the developer. Beware "two cowboys in a truck," would-be developers who want to lock up land without the money to deliver. Ask: "How many megawatts do you have in operation right now?"
- Do your homework before anyone knocks. Decide where data centers can go, how they must be built, and what you'll ask for. Companies want certainty of power and certainty of a fair, predictable approval process.
- Put them out of sight, out of mind. Designate locations with large buffers away from homes, schools and churches. Large campuses look for 300–1,000 acres.
- Pick a zoning tool. By-right in a designated zone, a conditional use permit, or a technology overlay district, with setbacks, height, screening and a strong noise ordinance.
- Set your tax rate now. "If you don't have a tax rate, you may want to start thinking about that." Don't accelerate the equipment depreciation schedule.
- Know your five layers: power, water, land, fiber, and community willingness, which was called the most important today.
- Get a power agreement, not a power promise. A capacity "snapshot" isn't an electric service agreement.
- Negotiate community benefits. Expect a community benefits package on top of the project itself.
- Plan the money and the message. Get third-party eyes on revenue estimates, update your capital improvement plan, don't spend revenue before it arrives, and have a communications plan.
- It's okay to say no. You can turn down hyperscale campuses and still welcome small data centers, or decline entirely.
Know who you're dealing with
Two speakers raised this, and it was one of the most important messages of the day: work with the right team. That means verified developers, plus your own attorney, engineer, utility contact and regional partners.
Signs of a serious developer
- Has megawatts operating today, and will let you tour a facility
- Has, or is actively pursuing, a signed electric service agreement with the utility
- Pays for studies and infrastructure up front, and accepts up-front commitments or back-out penalties
- Has actually visited your community and the site
- Commits to neighbor outreach before construction
Red flags
- Talks only about "planned" or "pipeline" megawatts
- Wants long-term land options without paying for studies or infrastructure
- Pushes for a fast decision or for you to skip steps
- Won't explain where the money comes from
One panelist described walking away from a billion-dollar project because the company wouldn't visit the community, and the board supported the decision.
Where to check credentials
Before you rely on anyone, confirm they are who they say they are. These are Virginia links. Other states have their own versions: search "[your state] professional license lookup" and "[your state] business entity search."
- Virginia DPOR License Lookup: engineers, contractors, surveyors
- Virginia SCC Clerk's Information System: shows whether a company is registered and in good standing
- Virginia State Bar: attorney member lookup
- National Association of Counties (NACo): recommended at the workshop for data center best practices
- Your regional planning district commission (PDC) or regional council, which can help arrange a visit to an operating data center
9:10Data Center 101
- Data is now a utility, like electricity or the interstate system, and data centers are the infrastructure that delivers it.
- New technology goes through three phases: rejection and panic → regulation and adaptation → ordinary infrastructure. Public opinion on data centers is in the panic phase right now.
- Data centers range from small enterprise facilities (a bank's own servers) to colocation sites to huge hyperscale campuses run by companies like AWS, Google and Microsoft.
- For every direct data center job, he cited 4–6 indirect jobs in construction, food service, hospitality and supply.
- "Capital advantage": servers and equipment are replaced every 3–7 years, which keeps refreshing the local tax base. Ordinary factory equipment just depreciates.
- Know who regulates what. Localities handle the comprehensive plan, zoning, setbacks, screening and noise. The state (DEQ in Virginia) regulates air permits for backup generators, water and stormwater.
- Be proactive: set aside land for industrial uses and adopt setbacks, screening and a sufficient noise ordinance. "Noise is a land use issue."
- If your locality doesn't have a tax rate for this equipment, start thinking about one now. Rates vary widely across Virginia.
- Example: one county designated a single site and set 500-foot setbacks, height limits and noise rules, with data centers by-right there. A company came in knowing exactly what was required.
- Most new data centers use closed-loop cooling, not evaporative. He said comparing the two is "like comparing a Model T to a Tesla."
10:00Siting & Construction
Matt Rowe, Pittsylvania County EDA · Matt Conrad, V.P., Business Development & External Affairs, Tract · Greg Vlassopolos, Account Manager/Data Centers, Schneider Electric
The five things a site needs
- Tract looks for at least ~300 acres, ideally 300–1,000. That leaves large buffers, such as 500 feet of existing pine stands, so the campus is "out of sight, out of mind," away from neighborhoods, churches and schools.
- Be ready to show about 100–150 MW of initial power for the first two or three buildings. Natural gas is becoming just as important.
- Equipment has very long lead times, so suppliers join site conversations early. AI chips have pushed rack power from about 11 kW to 135–155 kW. Above about 40 kW, racks need closed-loop liquid cooling.
- Labor is short: the average engineer in these buildings was said to be 54 years old.
- Jobs: Tract's research estimates about 39 permanent jobs per 100 MW, from security and groundskeeping to skilled technicians. Construction brings thousands of temporary workers for years.
- Housing: Pittsylvania County/Danville estimated a need for 1,000 more dwelling units by 2029 for its mega-site project.
- Taxes: Pittsylvania set its equipment rate at $1.62 per $100. The advice: do not accelerate the depreciation schedule. It used 15 years, like any other business, rather than dropping to 5% in five years.
- Expect a community benefits package on top of the project itself.
- Power companies now require serious developers to put large sums down up front and accept back-out penalties, so speculators are falling away.
- Construction is intense: truck traffic, road wear and generator noise. Viral "data center noise" videos often record construction generators, not an operating facility.
- Recommended: tour a modern data center (your regional council or PDC may organize it), and use National Association of Counties (NACo) resources.
11:00Community Benefits
David Manley, Executive Director, Virginia Tobacco Region Revitalization Commission · Anthony Romanello, Managing Partner, SIR (former Henrico Co. EDA) · Jeremy Satterfield, TechSpark Manager, Microsoft · Alex Gottschalk, Mecklenburg County Administrator
- Mecklenburg County: data centers are the largest taxpayer, about 45% of the real estate portfolio on less than 1% of the land. The revenue helped build new schools without raising the sales tax.
- Henrico County: data centers in a technology park were by-right. After opposition, the board began requiring a conditional use permit elsewhere in the county. Data center revenue funded a $12 million-a-year affordable housing trust for five years.
- Microsoft Data Center Academy (since 2011, with Southside Virginia Community College) has graduated about 1,300 people, who now work at schools, banks, hospitals and elsewhere, not just Microsoft. Microsoft also funded school greenhouses and now publishes its water and electricity use.
- Supply chain wins: suppliers such as JST Power Equipment (~50 jobs) and Hitachi Energy (~120 jobs) followed the growth. Local electricians, landscapers, metal shops and food services benefit from ongoing maintenance.
- Get third-party eyes on the revenue estimate (one example: $10–15 million a year in tax revenue per $1 billion invested) instead of relying on one person's math.
- Don't spend the money before it arrives. Update your capital improvement plan, be deliberate, and build a communications plan, inside your government as well as with partners.
- Good developers do door-to-door outreach before earthmoving. One builder went house to house with a card: "Any questions or concerns? Let me know."
- Expect opposition, sometimes from outside groups even when local residents are supportive.
- Plan for digital infrastructure and broadband more broadly. You can say no to hyperscalers and still welcome small data centers.
12:10Keynote
- Scale: McKinsey projects a $3.7–8 trillion market through 2030, a little over 2% of GDP, about 10× the Apollo program's share.
- Growth is moving south and west in Virginia along I-95 and I-81 as Northern Virginia (Loudoun, Prince William) nears saturation.
- Loudoun County: about $900 million a year in data center tax revenue for schools and real estate tax relief. Mecklenburg essentially rebuilt its schools with cash.
- Virginia saw about $24 billion in data center investment in 2023. The state's sales tax exemption on data center equipment is roughly $1.7 billion a year.
- Rule of thumb cited: about 50 jobs per floor, or per 250,000 sq ft. Many roles are technicians, HVAC and logistics trained through community colleges, not four-year degrees.
- Electricity costs: data centers aren't the only cause. Regulation and an aging grid with little investment play a big part.
- Water: about 17 billion gallons a year statewide, which he said is far less than agriculture or golf courses. Air cooling uses less water but more electricity.
- National opinion has shifted toward opposition, but support grows when residents see local benefits like school funding and lower taxes.
- Technology overlay districts keep data centers away from homes and protect property values. Spotsylvania County was mentioned as doing this well.
Questions to ask any developer
Collected from across the day.
Size & scale
- How many acres, including buffers and future expansion?
- How many buildings, how many square feet, and how tall?
- How many megawatts at opening, and at full build-out?
- Is this hyperscale, colocation, or a small enterprise facility?
- How many phases, and how long will construction last?
Credibility
- How many megawatts do you have under operation right now?
- How will you fund studies, infrastructure and construction?
- Who is the end user or operator?
- Can we tour one of your operating facilities?
- Will you accept up-front commitments or back-out penalties?
Power, water & generators
- What is the total electric load? Do you have a signed electric service agreement?
- Will it require new transmission lines or substations?
- Closed-loop or evaporative cooling? What is the water source and daily volume?
- How many backup generators, and what are the permit operating limits?
- Noise levels at the property line, lighting and screening?
Taxes, benefits & construction
- What tax terms and depreciation schedule are you proposing?
- What will you put in a community benefits agreement? Local hiring and training?
- Truck routes, road repair, and where construction workers will live?
- How and when will you contact neighbors?
Myths & facts
Claims you may hear at public meetings, with what speakers said in response.